NEPA By the Numbers – Where NEPA Draws the Line: Determinations of Significance
Data management, analysis, and visualization: Kasey Zapatka, PhD
Clean Air Task Force project team: Kelsey Landau, Nicole Pavia, Natalie Manitius, Alan Mitchell, and Frank Sturges
Project advisor: Keith J. Benes, Adjunct Professor and Senior Researcher, University of Nebraska-Lincoln College of Law
GitHub: https://github.com/kaseyzapatka/nepa/blob/main/phase2/architecture/deliverables/deliverable02.md
Browse environmental reviews for energy technologies with the NEPA Document Explorer: https://huggingface.co/spaces/kaseyzapatka/nepa-document-explorerhttps://huggingface.co/spaces/kaseyzapatka/nepa-document-explorer
A single word – “significant” – can determine how long a project takes to get through environmental review. Under the National Environmental Policy Act (NEPA), projects with a record demonstrating that the category does not normally significantly affect the environment may qualify for categorical exclusions, the fastest review pathway. Projects that do not have a reasonably foreseeable significant effect on the quality of the human environment, or where the significance of the impact is unknown, can be completed through environmental assessments, the mid-level review pathway. Environmental assessments that result in a Finding of No Significant Impact (FONSI) can proceed without a full environmental impact statement (EIS). But if a federal agency determines that a project would have reasonably foreseeable impacts that are significant, it must prepare an EIS, a process that can add years to the environmental review process. This analysis provides the first systematic look at how federal agencies make significance determinations for decarbonization projects.
Key Findings
- The majority of decarbonization projects that receive a FONSI rely on mitigation to get there. About 58% of FONSI decision documents analyzed found that a project would avoid significant environmental impacts only if the developer agreed to specific measures to mitigate those impacts. These measures most commonly address impacts to biological resources (30%), soils / geology (28%), water (26%), and cultural / historic resources (22%).
- Visual impacts are the most common reason that projects receive significant impact findings. Among projects reviewed through an EIS, visual impacts were more likely than any other resource category to be considered significant. About 33% of the documents analyzed included a significance finding related to visual impacts, and most identified at least some significant visual impacts as unavoidable.
- Some environmental impacts are more likely than others to remain significant. Impacts to soils and geology, water, and public health are generally more likely to be reduced below the significance threshold through mitigation. By contrast, impacts to visual resources, land use, and air quality are more likely to remain significant, even when mitigation measures are applied.
- Mitigation does much of the work – but is not always demonstrably enforceable. Developers often agree to measures that allow agencies to conclude that a project will not have significant environmental impacts. However, those commitments are not always incorporated into enforceable permit conditions. This is particularly common for measures addressing cultural resources, soils, and public health.
Introduction
The National Environmental Policy Act (NEPA) is a foundational environmental law that has, for more than fifty years, ensured that federal agencies consider the environmental impacts of a proposed major federal action. NEPA requires federal agencies to consider the reasonably foreseeable environmental impacts of their activities, integrate those considerations into agency decision making, and enhance public transparency in the decision-making process.
There are three levels of review in NEPA, which are determined based on the expected significance of a project’s impact on the human environment:
- Categorical exclusions (CEs), the fastest pathway, cover a class of actions that an agency has determined, based on a documented history of past experience, does not normally have significant environmental effects.
- Environmental assessments (EAs), the mid-level of review, are prepared for agency actions that do not have a “reasonably foreseeable significant effect”1 on the quality of the human environment, or if the significance of such effect is unknown; agencies have a statutory limit of one year to complete an EA. EAs may result in a Finding of No Significant Impact (FONSI); if impacts are found, throughout the course of preparation, to be significant, then an environmental impact statement (EIS) must be prepared instead.
- EISs, the most in-depth form of review, are required for agency actions with a “reasonably foreseeable significant effect” on the environment and have a statutory limit of two years to complete.2
The question of whether an action has “reasonably foreseeable significant effects on the quality of the human environment,” therefore, has notable implications for review timelines, potentially adding a year or more to the NEPA process. However, little is known about how agencies reach this important determination, with important information around which resources contribute to significance determinations, impacts on different technologies, and the role of mitigation completely nonexistent.
In this analysis, we fill this research gap by using the NEPATEC 2.0 dataset, part of the Pacific Northwest National Laboratory’s PermitAI project, to investigate significance determinations across EAs, FONSIs, and EISs for a suite of decarbonization-related technologies. The NEPATEC 2.0 dataset – which contains more than 120,000 NEPA documents from 60,000 reviews prepared by more than 60 different agencies in machine-readable JSON format – and machine learning make it possible to answer these questions systematically for the first time.
The diagram below details the vocabulary this report uses. Every determination lands on one of these outcomes, and “the line” is the significance threshold that separates the fast track from the full review:
Figure 1

Methodology
We analyze two document tracks separately, because they record opposite outcomes. FONSIs are the below-the-line record, where agencies concluded the impact is not significant and where the mitigated cases live. EISs are the above-the-line record: impacts the agency judged significant, and at the extreme significant and unavoidable.
The workflow pairs the scale of automation with the reliability of human judgment. We use complex code to locate specific passages with the significance findings within documents; a language model (Claude) then codes four variables – outcome, resource area, threshold, mitigation. Before any results are analyzed, the extraction is scored against a held-out answer key: a representative 400-passage sample per track, labeled independently by two AI coders with a human adjudicator settling every disagreement.
The two tracks together span a larger EIS corpus and a smaller FONSI corpus, and both touch every major resource area (Figure 2):

FONSI Analysis: How Agencies Stay Below the Line
Scope, coverage, and accuracy
The FONSI analysis rests on the decarbonization FONSIs led by BLM or the Department of Energy (DOE) and carry machine-extractable significance findings. Some documents phrase their findings in wording that the machine extraction doesn’t recognize and are therefore excluded from this analysis. The automated extraction process yields 258 decision documents across 193 projects and performs well in data validation. The analysis below is based on that subset of documents, not the full corpus.
How agencies stay below the line
Within FONSIs the determinations sit, almost without exception, below the significance line (Figure 3): the agency either finds no significant impact outright, or an impact that is less than significant, sometimes only with committed mitigation. The dominant outcome is no significant impact, as expected. But the resources agencies analyze most are also where the close calls concentrate: the committed-mitigation band is widest for biological, soils/geology, water, and cultural/historic.
Figure 3: How Agencies Stay Below the Line, by Resource

Mitigated FONSIs – The line itself
The most revealing determinations are the mitigated ones: impacts the agency says would be significant, brought below the line only by required mitigation measures. They show where the line sits and what is required to stay under it. They also comprise the majority of FONSIs – about 58% of the analyzed FONSI documents are mitigated (Figure 4), with at least one resource whose not-significant conclusion depends explicitly on committed mitigation.
Figure 4: Most Decarbonization FONSIs Reach “No Significant Impact” Only With Committed Mitigation

The mitigation burden is concentrated in a few resources (Figure 5) – biological (30%), soils / geology (28%), water (26%), cultural / historic (22%). Biological resources are both analyzed often and mitigated often, while soils/geology are mitigated intensively despite lower volume.
Figure 5: Which Resources Drive Mitigation

What do these mitigations actually look like? Table 1 gives a representative measure for each of the most mitigation-heavy resources:
Table 1: Representative mitigation measures behind less-than-significant-with-mitigation conclusions (one example each for the five most mitigation-heavy resources; verbatim from the FONSI).
| Resource | Example of mitigation drawn from a FONSI |
|---|---|
| Biological | Restricting construction to August/September is intended to mitigate potential nest failure and displacement effects on Red-throated Loons. |
| Soils / geology | Use of BMPs [best management practices] and implementation of a construction SWPP [stormwater pollution prevention plan] would ensure that short-term soil erosion and sediment transport impacts remain minor. |
| Water | Wetlands in the area were inventoried and potential impacts were mitigated in the design of the Proposed Action alternative. |
| Cultural / historic | KSU [Kansas State University] committed to minimize or avoid potential effects to cultural resources via protection measures detailed in section 2.5 of the EA. |
| Public health | With mitigation measures and BMPs [best management practices], fire-prevention measures and traffic management would prevent disruption to fire, police, and medical emergency services. |
Mitigation drivers differ by agency and technology
The Bureau of Land Management (BLM) and the Department of Energy (DOE) review different kinds of projects, so the resources that push them to mitigate differ too (Figure 6): biological, cultural/historic, air quality, and visual resources drive mitigation harder for BLM’s land-facing portfolio, while noise and water lean toward DOE’s facility- and construction-driven work.
Figure 6: Does a Resource Trigger Mitigation More for BLM or DOE?

The project type matters as much as the agency (Figure 7): transmission and wind more often rely on mitigation – linear corridors and turbine sites touch habitat, viewsheds, and cultural resources – while solar and storage sit at or below the corpus average.
Figure 7: What Technologies Lean on Mitigation?

Enforceability of committed mitigation
“Mitigated” only means something if the measures are actually performed. Performance becomes more likely if it is explicitly required by the terms of a permit. The analysis flags whether each mitigated conclusion is tied to an enforceable permit condition or committed only in the document’s text. The pattern tracks regulatory leverage (Figure 8): biological and air-quality conclusions – backed by the Endangered Species Act and the Clean Air Act, respectively—most often carry an enforceable permit condition (about half and 43%). Visual and water sit mid-range (36% and 35%; the visual cell is small, n = 14 mitigated conclusions), while cultural, soils/geology, and public-health measures are rarely tied to one (26%, 9%, and 8%).
Figure 8: Is the Committed Mitigation Actually Enforceable

EIS Analysis: Which Resources Cross the Line
Scope, coverage, and accuracy
The EIS track is the mirror of the FONSI track – the above-the-line record of where impacts actually cross the significance line. It runs the identical extraction-and-validation process detailed above but covers all lead agencies (not just BLM and DOE) because it is purely descriptive and never uses a project’s decision date. On that basis it evaluates 506 projects (1,082 documents) carrying 13,240 distinct determinations, of which 2,198 land above the line, including 698 judged significant and unavoidable—impacts mitigation cannot erase.3
Which resources cross the line
Ranking each resource by how often its EIS conclusions are judged significant (Figure 9), visual (33%) stands alone at the top, the clearest case of an impact that, once significant, tends to stay that way. Cultural / historic (24%), biological (21%), and land use (18%) follow.
Figure 9: Visual Impacts Cross the Significance Line More Than Any Other Resource

The starkest determinations are the significant and unavoidable ones – impacts no mitigation can bring below the line. Visual impacts dominate (Figure 10): a wind farm on a ridgeline or a transmission corridor across open country changes a landscape in ways no mitigation can fully undo. Biological, cultural, and air-quality impacts follow; Table 2 gives representative findings in the agencies’ own words.
Figure 10: The Wall: Significant Unavoidable

Table 2: Representative significant-and-unavoidable determinations, verbatim from the EIS (one example each for the five resources that hit the wall most often).
| Resource | Significant-unavoidable finding, in the agency’s words |
|---|---|
| Visual | With mitigation, impacts to scenic vistas would remain adverse and unavoidable (VIS-1). |
| Biological | The proposed project would result in major unavoidable adverse effects on desert tortoise habitat. |
| Cultural / historic | The project would cause direct and indirect adverse change to the significance of historic properties. |
| Air quality | Unavoidable air quality impacts due to dust generated during site preparation and construction. |
| Noise | Noise associated with Alternative 4 operations is identified as a long-term, unavoidable impact. |
Two ways a resource can be a problem
Analyzing the two tracks separately pays off in one picture (Figure 12), which plots each resource by how often it is mitigated below the line (FONSIs) against how often it crosses the line (EISs), with both tracks restricted to BLM and DOE so they are measured on the same footing:
Figure 12: Some Resources Get Mitigated Below the Line, Others Cross It

Three shapes emerge. Visual, land use, and air quality break above the line more often than they are mitigated below it, with visual being the extreme. Soils/geology, water, and public health show the opposite – frequently mitigated, rarely crossing – the impacts the toolbox of committed measures reliably handles. Cultural/historic (and to a lesser extent transportation and climate) straddles both sides, crossing into significance about as often as it is mitigated below it. Figure 12 should be read as a map of where effort would pay off: the cross-over resources (cultural/historical) are where a project is most likely to be pushed into a full EIS, and where mitigation practice is least developed; the managed-below resources are where the existing mitigation toolbox already works to keep a resource below the line.
Why an impact is significant
For every above-the-line determination, the extraction also records why it is significant. The leading reasons are sheer magnitude, a protected resource, and cumulative impacts (Figure 13; verbatim examples in Table 3). Most notable for “decarbonization” project siting is cumulative impacts: roughly one in four significance findings rests on impacts that build up across a landscape or airshed rather than on one project’s direct footprint.
Figure 13: Why an Impact is Significant

Table 3: What each significance factor looks like in the EIS text – verbatim examples for the five most common factors.
| Factor | Significant finding, in the agency’s words |
|---|---|
| Sheer magnitude | The Pier 41 Alternative could result in major socioeconomic impacts. |
| Protected resource | Alternative E would result in significant impacts to cultural resources. |
| Cumulative impact | The presence of the AEWP [Alta East Wind Project] would add to a cumulative visual alteration, as discussed above. |
| Regulatory threshold | VRM [Visual Resource Management] Class III objectives would not be met for this segment. |
| Significant but mitigable | Significant but mitigable impacts to parade-ground vegetation from irrigation with reclaimed water. |
Significance rates differ by lead agency
While all agencies complete EISs, some agencies’ EISs cross the line more often than others. Figure 14 shows that this pattern tracks each agency’s portfolio: the spread runs from the Army Corps of Engineers (27%) down to the Tennessee Valley Authority (3%), with land- and water-facing agencies (the Army Corps, BLM) crossing most often and utility-service programs least.
Figure 14: Does Crossing the Line Differ by Agency?

Significance by decarbonization technology
There are trends on which decarbonization technologies cross the line more than others. For example, Figure 15 shows that hydropower crosses the line most (28%), followed by transmission and solar; nuclear crosses least (6%) among the technologies with a large sample size. And the resources each technology most affects are distinct and largely predictable: wind’s resource is wildlife (avian and bat collision) and noise; solar’s is visual, cultural, and air quality; and transmission spreads across biological, visual, and cultural along its corridor.
Figure 15: What Technologies Cross the Line?

Significant, but reducible
Not every above-the-line finding is a hard stop: some significance determinations are flagged as still mitigable – the EIS analog of a mitigated FONSI. Visual determinations lead this list too (Figure 16): even the resource most likely to cross the line sometimes admits partial mitigation (screening, siting adjustments), just not enough to drop below it.
Figure 16: Significant but Reducible

Conclusion and Policy Implications
Mitigation plays a central role in whether an impact is called “significant.” A majority of the analyzed decarbonization FONSIs reach “no significant impact” only because the developer commits to specific measures, and that reliance is concentrated in a handful of resources (biological, soils, water, and cultural/historic sites), while others – notably visual – are mitigated far less often and, when significant, tend to stay that way. Two implications follow.
First, the uneven pattern is itself an opportunity. The resources that break above the line more often than they are mitigated below it – visual above all, along with land use and air quality – are precisely the ones where the mitigation toolbox is thinnest; increased investment in, and standardization of, mitigation approaches for those harder resources could keep more projects on the faster FONSI track, provided the measures genuinely reduce impact rather than relabel it.
Second, a caveat: the committed mitigation behind a not-significant finding is, more often than not, not tied to a demonstrably enforceable permit condition – especially for cultural, soils/geology, and public-health measures. This leaves open questions about the effectiveness of mitigation as a tool for avoiding in-depth environmental review: a finding is only as sound as the measures behind it are binding.
Data recommendation: standardize the terminology used for resource areas. The single largest friction in this analysis is that agencies name the same resource in many different ways, and significance language is written project by project. A shared, standardized resource-area vocabulary – of the kind contemplated by CEQ’s NEPA and Permitting Data and Technology Standard – would make significance determinations directly comparable across agencies and would sharpen every finding in this analysis.
Data: NEPATEC 2.0 – 193 decarbonization FONSI projects and 506 EIS projects. Methods and full results: Phase 2 Deliverable 2.
Footnotes
- 42 U.S. Code § 4336(b)(2)
- Three years for projects of “extraordinary complexity.” 42 U.S. Code § 4336a(e)(B)
- The EIS scores run lower than the FONSI track: the pipeline finds the determination reliably (0.84) and lands the significance class at 0.69 – separating “significant” from “significant and unavoidable” is a fine distinction the AI coders split on too. We therefore treat the adverse-vs-unavoidable split as directional.
Credits
Data management, analysis, and visualization: Kasey Zapatka, PhD
Clean Air Task Force project team: Kelsey Landau, Nicole Pavia, Natalie Manitius, Alan Mitchell, and Frank Sturges
Project advisor: Keith J. Benes, Adjunct Professor and Senior Researcher, University of Nebraska-Lincoln College of Law
GitHub: https://github.com/kaseyzapatka/nepa/blob/main/phase2/architecture/deliverables/deliverable02.md
Browse environmental reviews for energy technologies with the NEPA Document Explorer: https://huggingface.co/spaces/kaseyzapatka/nepa-document-explorerhttps://huggingface.co/spaces/kaseyzapatka/nepa-document-explorer